1) Which of the following sequence of phases are true according to ASAP methodology?
a) Project preparation > Realization > Blue print > go live > Final preparation.
b) Blue print > Realization > Project preparation > go live > Final preparation.
c) Project preparation > Blue print > Realization > Final preparation > go live
d) Project preparation > Blue print > Realization > go live > Final preparation
A: c
2) In which of the following phase the cut-over activities are carried out?
a) Project preparation
b) Blue printing
c) Realization
d) Final preparation
e) Go live and support
A: d
3) In which of the following phase the steering and other committees are formed?
a) Project preparation
b) Blue printing
c) Realization
d) Final preparation
e) Go live and support
A: a
4) In which of the following phase configuration is done in the ECC system?
a) Project preparation
b) Blue printing
c) Realization
d) Final preparation
e) Go live and support A: c
No comments:
Post a Comment